Project Planning

PERTCalculator

Estimate project durations using three-point analysis. Calculate expected time, standard deviation, and critical path.

Understanding PERT AnalysisLearn project estimation with three-point analysis

What is PERT?

PERT (Program Evaluation and Review Technique) is a project management method for planning and controlling complex projects. It uses three time estimates (optimistic, most likely, pessimistic) to calculate expected task duration and identify critical paths.

Why It Matters

PERT matters because: 1) Handles uncertainty - uses three estimates instead of one, 2) Identifies critical path - shows which tasks delay the project, 3) Improves accuracy - statistical approach reduces estimation errors, 4) Shows flexibility - reveals where slack exists, 5) Risk awareness - pessimistic estimates highlight potential delays.

Expected Duration

29.3 days

Std Deviation

±2.5

Critical Tasks

1

Total Tasks

5

Task Duration Estimates

Completion Confidence

PERT Task Analysis

TaskOptimisticMost LikelyPessimisticPERT ExpectedStd DevStartFinish
3.23.00.03.2
6.36.03.29.5
12.712.09.522.2
5.25.019.024.2
2.02.017.819.8
Project Total29.3±2.5

PERT Formula Reference

Expected Duration

E = (O + 4M + P) / 6

Weights most likely 4x more than optimistic/pessimistic

Standard Deviation

σ = (P - O) / 6

Higher = more uncertainty in estimate

Project Variance

σ² = Σ((P-O)/6)²

Sum of all task variances

PERT Calculator Glossary

PERT

Program Evaluation and Review Technique - a project management method using three time estimates for better planning.

Three-Point Estimate

Estimation method using three values: optimistic, most likely, and pessimistic to calculate expected duration.

Optimistic Time (O)

Best-case scenario estimate - everything goes perfectly. Represents about 1% probability of occurrence.

Most Likely Time (M)

Realistic estimate considering normal challenges. The most probable outcome based on experience.

Pessimistic Time (P)

Worst-case scenario estimate - everything that can go wrong does. Represents about 1% probability.

Expected Time

Weighted average using formula (O + 4M + P) / 6. Provides statistically most likely duration.

Standard Deviation (σ)

Measure of uncertainty/variability in estimates. Higher σ means less certainty in predictions.

Critical Path

Longest sequence of dependent tasks determining minimum project duration. Delays here delay the project.

Slack/Float

Time a task can be delayed without delaying project completion. Zero slack = critical task.

Variance

Statistical measure of uncertainty squared. Used to calculate project-level standard deviation.